Project Progress

12 Oct 2018:

Statue view from main street

12 Oct 2018:

Statue current status

09 Oct 2018:

Statue & Exhibition Hall (View From Dam)

09 Oct 2018:

Current Status of RCC, Steel & Bronze Work

09 Oct 2018:

Structural Steel Erection (100%)

09 Oct 2018:

Bronze  Steel Erection on October

09 Oct 2018:

Statue - Bronze Assembly

09 Oct 2018:

Exhibition Hall Garden Roof

09 Oct 2018:

Exhibition Hall - Interior Finishing Works

09 Oct 2018:

Exhibition Hall - Exterior Finishing Works

 

09 Oct 2018:

Main Approach Bridge

09 Oct 2018:

Memorial & Visitor Center, Ticketing Booth

09 Oct 2018:

Memorial & Visitor Center - Internal

09 Oct 2018:

Memorial & Visitor Center - Exterior Landscaping & Hardscaping 

09 Oct 2018:

STP & Service Building

09 Oct 2018:

M & VC Area Slope Protection Work

09 Oct 2018:

Road Works

09 Oct 2018:

Minor Bridges

09 Oct 2018:

Shrestha Bharat Bhavan

09 Oct 2018:

Shrestha Bharat Bhavan - MEP & Finishing Works

09 Oct 2018:

Shrestha Bharat Bhavan - Transformer

30 Sep 2018:

Shrestha Bharat Bhavan –Finishes

30 Sep 2018:

Shrestha Bharat Bhavan –Transformer

30 Sep 2018:

Shrestha Bharat Bhavan –Ancillary Buildings

30 Sep 2018:

Shrestha Bharat Bhavan –Service Building

30 Sep 2018:

Shrestha Bharat Bhavan

30 Sep 2018:

Panchamuli Bridge

30 Sep 2018:

Suryakund Bridge

30 Sep 2018:

Road Works

30 Sep 2018:

Service Building

30 Sep 2018:

Land Scaping Works at M & VC

30 Sep 2018:

Overall View from Dam Side

30 Sep 2018:

M & VC – Ticketing Booth

30 Sep 2018:

Memorial & Visitor Center

30 Sep 2018:

Main Approach Bridge - Columns for Tensile Fabric Canopy

30 Sep 2018:

Main Approach Bridge

30 Sep 2018:

Statue Base - Garden Roof

30 Sep 2018:

Statue Base Finishes

30 Sep 2018:

Column Cladding Works - Internal

30 Sep 2018:

MEP Works

30 Sep 2018:

Column Cladding Works - External

30 Sep 2018:

TMD  - Core A

30 Sep 2018:

Viewing from Viewing Gallery

30 Sep 2018:

Bronze  Steel Erection on September

30 Sep 2018:

Structural Steel Erection

30 Sep 2018:

Front & Rear view of statue

16 Sep 2018:

Bronze Erection

16 Sep 2018:

Structural Steel Erection

06 Sep 2018:

Statue View from Main Bridge

06 Sep 2018:

Overall View of Statue

15 Feb 2018:

Statue & Statue Base

15 Feb 2018:

Statue – Structural Steel

15 Feb 2018:

Statue – Bronze Erection

15 Feb 2018:

Pre Assembly in Bronze Yard

15 Feb 2018:

Statue Base Entrance

15 Feb 2018:

Progress Works in Statue Base

15 Feb 2018:

Main Approach Bridge

15 Feb 2018:

M & VC Building

15 Feb 2018:

Service Building

15 Feb 2018:

Service Building/M&VC -MEP

15 Feb 2018:

Road & Gabion Works

15 Feb 2018:

SBB Hotel Building

20 Sep 2017:

Statue –Core Wall & Coupling Wall

20 Sep 2017:

Statue Base - Bird’s Eye View

20 Sep 2017:

Statue Base- Drum wall

20 Sep 2017:

Sloping Roof-Structural Steel @ Zone-5

20 Sep 2017:

Main Approach Bridge - View From M & VC - View From Statue Base

20 Sep 2017:

Main Approach Bridge- Bottom Elements Erection

20 Sep 2017:

Main Approach Bridge- Precast Bottom Elements Yard

20 Sep 2017:

M&VC; Building

20 Sep 2017:

Road & Gabion Works

20 Sep 2017:

Minor Bridge – Panchamuli Bridge

20 Sep 2017:

Minor Bridge - Suryakund Bridge

20 Sep 2017:

Minor Bridge- Precast Girders

20 Sep 2017:

Service Building & STP at M&VC;

SBB hotel Building.

15 Jul 2017:

SBB hotel Building.

15 Jul 2017:

Statue Corewall.

15 Jul 2017:

Service Building & STP.

15 Jul 2017:

Statue base & Arches - Bird's Eye view of Statue base.

15 Jul 2017:

SBB hotel Building.

15 Jul 2017:

Road and Gabion Works.

15 Jul 2017:

Minor Bridges - Bridge Abutment works in progress.

15 Jul 2017:

Main Bridge precast Elements.

15 Jul 2017:

Main Bridge connecting Sadhu Hill.

15 Jul 2017:

Main Bridge - Overall view of main approach bridge

15 Jul 2017:

M & VC Structural Filling

15 Jul 2017:

M & VC Building

15 Jul 2017:

Erection of Precast Girders & Bottom Slab Elements

15 Jul 2017:

Drum Wall

25 Jun 2017:

Statue Core wall, Statue & Statue base, Statue base Arches, Main Approach bridge and M & VC service Trench are getting about to complete

09 Jun 2016:

Foundation PCC works

Statue foundation works

09 Jun 2016:

Statue foundation works

All footings for bridge

09 Jun 2016:

All footings for bridge

01 Feb 2016:

It takes a lot of infrastructure to build the World's Tallest Statue! Facilities that can accommodate up to 800 workers have been built at Sadhu bet. This includes living areas, Kitchen block, toilet block, grocery shop, first aid center, sewage treatment and water tanks in addition to quality lab.

29 Jan 2016:

A detailed monsoon preparedness plan has been created in order to ensure that construction at the Statue of Unity site proceeds with minimal disruptions during the 2016 monsoon season.

22 Jan 2016:

The museum and memorial park of the Statue of Unity will be completed before the construction of the feet of the Statue begins next year. The project is progressing on schedule and will be completed by 2018.

20 Jan 2016:

Before construction work on the feet of the‬‬ Statue of Unity begins next year, the construction of the main bridge connecting the statue to the Narmada bank as well as the road along the bank leading to Sadhu Bet will be completed.

18 Jan 2016:

As of December 2015, over 80% of rebar cutting and bending works for the Statue of Unity main raft foundation has been completed on site. More than 60% of rebar tying works and over 50% of formwork for the main raft as also been completed.

12 Jan 2016:

All concreting work for the confinement wall being built around Sadhu Bet will be completed by February, 2016

09 Jan 2016:

Geotechnical survey, Scleaning, Anti-termite treatment & plain cement concrete (PCC) for the Statue of Unity's raft foundation has been completed. RCC for the Statue's base is currently in progress.

07 Jan 2016:

Over the next few days, close to 4,000+ cubic meters of concrete will be compressed with ice in a process that follows precision, so as to ensure that there is no heat in the mixture, and be used to finish the raft foundation of the Statue of Unity

05 Jan 2016:

The 3-meter deep raft foundation of the Statue of Unity will now see round-the-clock concreting over the next few days to ensure a safe bearing capacity.

08 Dec 2015:

Cleaning, shuttering, and filling work in progress for the Statue of Unity concourse area at Sadhu Bet.

04 Dec 2015:

Rebar being fixed for the main statue raft at Sadhu Bet

02 Dec 2015:

Bund wall (embankment wall) under construction around Sadhu Bet.

27 Nov 2015:

Here's a glimpse of the on-site progress of the Statue of Unity construction. Much of the foundation has been built, while construction of a bund wall (confinement wall) around Sadhu Bet is in progress.

23 Jul 2015:

Bailey bridge is a temporary bridge being constructed to facilitate the movement of men, materials and equipment for the construction of the Statue of Unity even when the Sardar Sarovar Narmada Dam is overflowing, thus ensuring that construction work will continue during monsoons.

21 Jul 2015:

Excavation for the Statue base has been completed and excavation for entry and exhibition hall is in progress. The project office set-up at Sadhu Hill will allow all engineers working on the Statue and related components to operate efficiently on-site.

08 Jul 2015:

So far, four public consultation workshops have been organized at karamsad, Bardoli, Gandhinagar and Ahmedabad for taking feedback on the design of the Statue of Unity from citizens and making appeals for donating artifacts related to Sardar Vallabhbhai Patel.

06 Jul 2015:

The collection of Artifacts linked to Sardar Patel’s life and work has been initiated from various state archives and leading national museums.

04 Jul 2015:

A committee of historians and museum experts has been constituted for the selection of Sardar Vallabhbhai Patel related artifacts and archival material that will be placed in the exhibition hall in the base of the Statue of Unity

16 Apr 2015:

A detailed light and shadow study for the Statue of Unity has been conducted; hence we now know how it will look at a particular time on any day of the year. The actual orientation of the Statue is currently being finalized on the basis of this study and other economic considerations.

13 Apr 2015:

All Geo-technical and Hydrological surveys at the Statue of Unity site have been completed. Wind Tunnel tests to begin shortly.

03 Apr 2015:

A team of engineers is currently visiting bronze casting and exhibition design factories to study the latest technologies and quality standards, so that the same can be applied during the construction of the Statue of Unity